A full and fine building day allowing the team to get the front of the building clad and then to complete the second dormer as the plumbers got on with the task of connecting up the bath, basin, shower and hot-water tank under the stairs. Steve and I fitted the windows into the two frames that are now complete, and I will soon be getting the windows glazed.
Slow again to start work on a morning colder than of late but still made it by 8.00am. The weather was kind to us today and allowed the team to get the front of the building clad and then to complete the second dormer. Both of the plumbers arrived today and got on with the task of connecting up the bath, basin, shower and they also finished commissioning the non-vented hot-water tank under the stairs. I had to make another purchasing trip to Jewsons today - hopefully the last - and this should see us through to completion next week. This evening, Steve and I fitted the windows into the two frames that are now complete and I will soon have to think about getting the windows glazed.